PERMIT STATUS

Plan Review Comments Update

Last week I posted about some of the early plan review comments that had been posted for the Starter Home 2.0 project and it has now come to the point where all the plan review comments from the City of Cincinnati Building and Zoning Department, Fire Department, Metropolitan Sewer District and Water Works have been posted online and sent to me in letter form for my responses. The full list of comments is public record and can be found online here. My hope is pick-up the majority of the comments over this upcoming weekend in a series of response letters and drawing revisions, which I will review with the surveyor and contractor next week for their input before forwarding them on to the plans reviewers for what I hope is final permit approval. Once permit is in hand, I will be looking at an early-mid March construction start.