Slab Pour & Block Grouting
On Thursday the detached garage floor slab was poured and the concrete blocks were grouted solid with anchor bolts embedded into the grout for wall framing. The slab was pinned into the foundation wall and reinforced with rebar to allow the slab to stay solid in the event of any settlement and everything is sloped to the garage door for drainage. Control joints were formed in the slab to limit cracking and a portion of the block is left out at the front corner of the garage for a door to be installed out onto to the patio