Plumbing & Mechanical Progress
The plumbing and mechanical contractors were back at it again on Thursday, moving forward with the installation of pipe and duct runs. In terms of plumbing work, the initial Drain Waste and Vent (DWV) pipe rough-ins were completed and prepped for testing, the bath tub was delivered on site, and the first of the supply pipes were installed for the bath and shower. With regards to mechanical work, the supply duct fabrication and installation was nearing completion while the return duct fabrication and installation was just getting underway. Overall, I have been very pleased with how the plumbing and mechanical rough-ins have progressed the past few days, and am looking forward to seeing what gets accomplished on the Starter Home 2.0 site today.