Monday, May 11, 2015

WEEKEND ROOF WORK

Roofing Underlayment Installed 

This past Saturday the roofers took advantage of another nice weather day by installing all the underlayment for the asphalt shingles, which are scheduled to be installed early this week. The 9/12 roof pitch of the Starter Home 2.0 necessitated the temporary installation of 2x4's along the length of the roof to serve as additional footholds for the roofing crew, since it is slightly steeper than what is standard in many homes.