CRITICAL PATH ACTIVITIES

A MOMENTARY BREAK IN THE ACTION

In construction, the term 'Critical Path' is used to describe the longest sequence of activities in a project plan which must be completed on time for the project to complete on due date. An activity on the critical path cannot be started until its predecessor activity is complete; if it is delayed for a day, the entire project will be delayed for a day unless the activity following the delayed activity is completed a day earlier.
Unfortunately, two incomplete 'Critical Path' activities of Duke hooking up the power, and a missing interior railing arriving on site are now holding up subsequent activities until the start of next week. That said, despite the momentary pause in the action, the project is still tracking ahead of schedule, so it's nothing to be too concerned about. So until things pick-up again on Monday, here is a picture I took Thursday of the left hand side of the building in honor of 'Left Handers Day'