Monday, December 7, 2015

AS-BUILTS

Pleasant Ridge Project Wrap-Up 

This week I will be starting the final step in closing out the Starter Home 2.0 Pleasant Ridge project, which is updating the drawings and Revit model to reflect the actual 'As-Built' conditions. This is standard procedure with most all construction projects (especially for commercial ones) and the idea is to document any differences in the design that was drawn, vs what actually got built. Below is one example of an as-built revision for which I adjusted the floor-to-floor height to accommodate the standard stud length for a 9'-0" high finished ceiling.