FOOTERS POURED

Concrete Work Underway

In an effort to beat the rains expected this weekend in Cincinnati, the excavation and concrete contractors were hard at work all day Friday trenching, forming and pouring the footers for the Oakley Home 2.0 house and attached garage. The varying soil conditions across the site resulting from topography changes and the old construction debris left from the previous home and demolition required additional trenching and concrete beyond what was originally anticipated in spots, but thanks to effective construction management and collaboration with the city inspector and geotech engineer on the project, everything was able to get completed as hoped for. Below are some images of the freshly poured concrete footings and many more photos can be found by clicking here.