TRIM THIS, TILE THAT

Trim & Tile Work Progress

On Tuesday the Tile and Trim crews were both back at the Oakley Home 2.0 site and below is a brief summary with pictures of the work performed.
  • The trim carpenters continued to install kitchen cabinets, pieces of baseboard trim running up the stairs, and casing around the man door to the garage.
  • The tile workers finished installing the last few runs of wall tile around the basement corner shower and also grouted all the wall tile surrounding the various tub and shower units in the home.