Home 2.0 Blog Archive

Thursday, June 25, 2015

DRYWALL INSTALL

Inspections Passed & Drywall Started

With the Starter Home 2.0 having passed the HVAC ductwork, above ground plumbing rough-in, and insulation inspections, recorded on the ezTrak website (here), the drywall crew was given the go ahead to start hanging the gypsum wall board on Wednesday. The crew, which is only two guys, was close to having the interior of the house completely sheathed when I was on site around 5pm and still working, so I'm anxious to see where everything is at later today.