LEVELS OF ACTION

Basement, 1st Floor, 2nd Floor & Roof Activity

The workweek got off to an action-packed start at the Oakley Home 2.0 site on Monday with construction work happening in the basement, on the 1st floor, 2nd floor, low roof and high roof. Here is a summary of what all went down on each level over the course of the day.

Basement Activity: Interior wall framing in the basement was completed and plumbing rough-ins for the basement restroom and laundry were started.
1st Floor Activity: Stairs were delivered and put in place while plumbing rough-in work wrapped up. Additional blocking was also added in the garage for the garage door, operator and track support.
2nd Floor Activity: Additional plumbing rough-ins for waste, vent and supply lines were installed.
Low Roof Activity: Rubber roofing was installed over the tapered joists and sheathing for the walk-out roof deck above the front porch and garage.
High Roof Activity: The ridge vent was installed along the peak of the main roof.
Will this fast and furious pace continue throughout the week? Check back with the Home 2.0 Blog to find out?