Tuesday, October 31, 2017

OAKLEY HOME 2.0 VIDEO BLOG UPDATE 19

Halloween Edition

This is episode 19 in a series of updates on the Oakley Home 2.0 @ 3874 Isabella project that will serve as a supplement to my other Home 2.0 Project Blog Posts.
  • Topics Include: Construction recap and look ahead to final close-out

Monday, October 30, 2017

ATTIC ACCESS

NEW CEILING OPENING CUT

One of the things that I try and make clear with the contractors and subcontractors I work with on my Home 2.0 projects is that I'm always open to suggestions for how to improve the project if there is a better way of doing something than what I show on my drawings. I might not always go along with it, but I will be sure to at least listen. One such suggestion that is being implemented came months ago from the lead framer to relocate the attic access opening in the ceiling to not be in the second floor hallway as shown on the plans, which is a highly visible location. Instead, it was agreed to move that opening to the master bedroom closet to be more out of sight. That opening was cut in last week and will provide a place for the insulation crew to get up in the attic and spray insulation above the ceiling in upcoming weeks.

Sunday, October 29, 2017

THE BOSCH KITCHEN

Appliance Selections

Last week I met with the distributor I'm working with to supply appliances for the Oakley Home 2.0 @ 3874 Isabella on-site to finalize kitchen appliance selections for the house and below are the products chosen, which have also been added to the 'SELECTIONS' page on OakleyHome2.com website. The line of appliances I have decided to go with is Bosch, which combines sleek European design with exceptional performance to be recognized as one of the most desirable and reliable luxary kitchen brands. Below are some specifics on the Refrigerator, Gas Range, Vent Hood, Dishwasher and Microwave that will be in the weeks ahead.









  • The Bosch Dishwasher includes a flexible 3rd rack to accommodate deeper items and adjustable tines to customize the rack’s loading space.


  • The Bosch Microwave's large cooking interior provides the flexibility to cook various dishes and is a perfect match to the sleek design of the Bosch Kitchen.

Saturday, October 28, 2017

BURIED GAS LINE BELOW

Gas Line Installation

With sewer, water, and electric all installed at the Oakley Home 2.0 project, groundwork on the final utility hook-up began Friday with the marking, digging, and running of conduit for the natural gas line from the street to the house. The plumber will install the gas meter along the side of the house in the next few weeks. 

Friday, October 27, 2017

TRIM PROGRESS WALKTHROUGH

1st Floor Trim & Cabinetry Video Tour

Below is a video walkthrough of the first floor of the Oakley Home 2.0 highlighting the in-progress trim and cabinetry installation. 

Thursday, October 26, 2017

POWER & POSTS

Permanent Power & Deck Posts Installed

Wednesday was an action packed day on on the exterior of the home with the installation of permanent power from the street taking place along with the main deck posts and deck beam getting set. Below are a few images of these construction activities.

Wednesday, October 25, 2017

SWITCHES

Light Switch & Plug Installation

Tuesday marked the return of the electrician to the job site with switches and plugs being placed in the blue plastic gang boxes that were installed during the rough framing phase of construction. Permanent power hookup to the house is scheduled to take place within the few days, which will allow for the removal of the temporary power pole in the front yard, the underground gas line installation, and finish grading following shortly thereafter.

Tuesday, October 24, 2017

SLIDING DOORS & MORE

Sliding Closet Doors & Ongoing Trim Work

A lot going on over at the Oakley Home 2.0 @ 3874 Isabella project Monday with the trim carpenters working all day on everything from installing the sliding pantry/closet doors, to continuing to trim around the doors and windows, to getting started on installing the baseboard trim. One of the details worth mentioning that I took a picture of is how the baseboard trim and base cabinets are held off the ground 3/4" to accommodate the depth of the pre-finished hardwood floor that will be installed.  

Monday, October 23, 2017

WE'VE GOT CABINETS

Kitchen & Vanity Cabinetry Installation

Sunday was a day of work over at the Oakley Home 2.0 project site with the kitchen base and wall cabinets along with the bathroom vanity cabinets getting set in place. Below are some progress shots of the installation so far and many more can be found in the Oakley Home 2.0: Album 2 Blog link.

Sunday, October 22, 2017

BACK YARD WORK

Extreme Weed Whacking

On Saturday I took a weed whacker over to the Oakley Home 2.0 site to cut down the forest of tall grass and weeds in the back yard that had sprouted since Spring. Below is a 'before' and a couple 'after' shots of the yard work, which ended up being quite a transformation.

Saturday, October 21, 2017

OAKLEY'S NEXT GENERATION OF HOME IS HERE

Draft of Oakley Home 2.0 Article for Publication

One of the ways to pick-up a LEED for Homes credit in the category of Awareness & Education (AE) is to have a 'Newspaper' article on the project published mentioning some of the sustainable design features being incorporated into the home. The term 'Newspaper' includes blogs, newsletters, and other media that are readily available to the public, and below is a draft version of what I am sending out in advance of publication. I imagine the language will get tweaked and the renderings might be substituted out for actual photos as construction progresses, but feel like this is a good start in telling the story of the Oakley Home 2.0 @ 3874 Isabella to a larger audience.

Oakley’s Next Generation of Home is Here
With its central location, thriving business district, and numerous parks and recreation spaces, it is easy to see why Oakley is widely recognized as one of Cincinnati’s Hottest Neighborhoods and has attracted waves of new homebuyers over the past decade. Unfortunately, the lack of contemporary new homes that feature the modern amenities and efficiencies new build construction provides has made it difficult for growing families to stay in the neighborhood long-term as the need for more bedrooms, bathrooms and entertainment spaces becomes a priority for households in future years. The time is now in Oakley for this next generation of new home construction to become a reality and the soon-to-be-completed 4 bedroom, 3-½ bathroom single-family LEED Gold residence at 3874 Isabella Avenue offers that and much more.
2016-12-26_OakleyHomeExterior2People.jpg
Featuring an open plan layout with dynamic indoor/outdoor living spaces on all three levels, the Isabella home’s modern interior amenities range from a master suite, to breakfast bar, to reading nook with quality finishes throughout the dwelling that include solid Oak hardwood floors, quartz countertops, and glazed ceramic floor and wall bath tile. The exterior of the home delights as well with an expansive rear deck opening up off of the main living area, a walkout basement patio, covered front porch, and a second floor roof deck. This LEED Gold home (eligible for a 15-year tax abatement worth up to $562,000) also showcases numerous sustainable design features such as double thick wall insulation and enhanced air sealing to save energy; high efficiency toilets, faucets and shower heads to conserve water; Pre-cut framing packages to reduce material waste; and increased ventilation, exhaust and air filtering using Energy Star bathroom fans and filters to ensure a clean, healthy living environment for residents and guests alike.

Interesting in learning more about this home at 3874 Isabella Avenue currently for sale and ready for occupancy at the end of November? Visit the full listing by clicking here.
2017-08-19_OakleyHome2-Kitchen.jpg

Friday, October 20, 2017

SELECTION PAGE UPGRADE

OakleyHome2.com Selections Tab Additions

I previously blogged about the selection section added to the OakleyHome2.com website, but have since expanded the list to include bath finishes and fixture selections. Below is a screen grab showing a portion of that page and the complete version can be found on OakleyHome2.com.

Thursday, October 19, 2017

ALL THE TRIMMINGS

Window Trim & Door Casing Progress

The trim carpenters were back at work on Wednesday to get a start on installing the trim around the windows and casing around the door frames previously shimmed into place throughout the interior of the Oakley Home 2.0 project. The trim used in this project is pine, which not only has a great finish look when painted, but is also highly durable and resilient to moisture (unlike MDF, which swells up like a balloon when exposed to just a little water). Below are some images of the day's work.

Wednesday, October 18, 2017

SETTING DOORS

Interior Doors Shimmed In Place

Earlier this week the trim carpenters made their first appearance on the Oakley Home 2.0 site, setting the the interior doors into place throughout the home with shims. Note that the black hinges will be changed to satin nickel finish as part of the final project punch list.

Monday, October 16, 2017

DIRT PILE

Getting to Finish Grade

Earlier today a load of dirt was dropped off at the Isabella lot to be spread around portions of the home to get areas closer to finish grade. Below is a picture of said dirt.

Saturday, October 14, 2017

COOL NEW TOOL FROM HOUZZ

View In My Room 3D

I've mentioned several times on the Home 2.0 Blog that Houzz.com is my #1 go-to site for all things related to residential design, and I recently discovered a cool new tool from their website that is a quick and easy visualization tool for furnishing a room. It is a feature called 'View In My Room 3D' that is available on the Houzz App you can download for free on your phone and tablet. The way the tool works is that you can scroll through the Houzz product gallery, select a piece furniture or decor that you think would be a nice addition to a given room, and see what it looks like in in real time (like the table and chairs shown in the Oakley Home 2.0 dining area below). You can scale, rotate and flip the products as needed to fit the specific camera angle selected. It isn't great for space planning, as there is no way to ensure that the scale of objects is exactly correct, but for the purpose of quickly visualizing and evaluating the aesthetic qualities of furnishing ideas, it is a highly effective resource.

Thursday, October 12, 2017

DECKED IN CLAM SHELL

Trex Decking Installed at Front Porches

On Wednesday the Trex 'Clam Shell' color deck boards were installed over the front porch joists and roof deck sleepers. With the roof deck being 21' wide and decking only coming in 20' long pieces, a 6" border was placed along the perimeter and mitered at the corners to make the most efficient use of material, while adding some aesthetic appeal. Below are some images of the installation and finished product. 

Wednesday, October 11, 2017

DECKING DELIVERY

Posts, Beams, Columns & Trex

Tuesday the materials for the porch and deck construction were delivered to the job site. The shipment included 6x6 posts and post anchors, 2x12 and 2x10 lumber for deck beams and joists, and Trex 'Clam Shell' composite decking.

Tuesday, October 10, 2017

MASTER BATH PREVIEW

New Master Bath Rendering

One of the areas of the Oakley Home 2.0 that is a signature design feature is the master bathroom off of the master bedroom. Below is a rendering that was recently generated previewing that space, updated to include the most current selections.

Monday, October 9, 2017

READY FOR THE WORKWEEK

Materials Stocked

Construction trades are traditionally broken down into 2 categories: Material and Labor. With respect to interior finish work, the Oakley Home 2.0 definitely has the material part covered. Now it is just a matter of catching up with respect to the labor. Stay tuned for updates.

Sunday, October 8, 2017

OAKLEY HOME 2.0 VIDEO BLOG UPDATE 18

Construction Schedule Preview

This is episode 18 in a series of updates on the Oakley Home 2.0 @ 3874 Isabella project that will serve as a supplement to my other Home 2.0 Project Blog Posts.
  • Topics Include: Construction Schedule Preview

Friday, October 6, 2017

STEPS FROM THE SQUARE

Site Context

Most of my Oakley Home 2.0 photos I post to this blog tend to focus on the details of the house itself, but don't give much context relative to the location of the home, which is one of its main selling points. Literally steps away from Oakley Square, the Panorama image below does a nice job of showing why the Oakley Home 2.0 project has a 'Very Walkable' Walk Score of 85

Thursday, October 5, 2017

WATER SENSE

LEED Bathroom Fixture Selections

One of the main LEED for Homes categories that points are awarded to in the rating system is Water Efficiency. I recently made several bathroom fixture selections for high efficiency faucets, shower heads, and dual flush toilets that will contribute towards credits in this category and ultimately to the LEED Gold Certification. These selections will also help in cutting down on water usage and provide savings of water bills for the future homeowners. Below are a few of the selections that were made.

  • Bathroom Faucets: MOEN Eva 4 in. Centerset 2-Handle High-Arc Bathroom Faucet in Brushed Nickel (Model # 6410BN)

  • Shower Heads: MOEN Envi 3-Spray 4 in. Eco-Performance Showerhead in Brushed Nickel (Model # 3233EPBN)

  • Toilets: American Standard H2Option 2-piece 0.92/1.28 GPF Dual Flush Elongated Toilet in White (Model # 2887218.020)

Wednesday, October 4, 2017

PREPPED FOR POWER

Electric Panel and Service Drop Installation

Earlier this week in preparation for the local utility company (Duke Energy) to be able to hook-up the permanent power connection to the Oakley Home 2.0, the main electric panel in the basement and service drop to the meter box on the exterior of the house were installed. Below are some images of this work and now it is just a matter of waiting on Duke to get a crew out on site and connect the power supply from the street to the service drop.

Tuesday, October 3, 2017

GARAGE DOOR INSTALL

Garage Door, Operator & Accessories

On Monday the 9'-0" wide by 8'-0" tall garage door was installed at the Oakley Home 2.0 project along with the garage door opener, garage door operator, keypad, motion sensors and weather stripping. The door itself will eventually be painted black on the exterior to match the window frames, gutters and downspouts.